Nuclear program will bring more power

By Jiang Xueqing reports from Shenzhen and Wu Wencong from Beijing (China Daily) Updated: 2012-12-24 07:39

Comprehensive studies conducted after the disaster in Fukushima will help ensure safety and high standards, Jiang Xueqing reports from Shenzhen and Wu Wencong from Beijing.

The meltdowns at a Japanese nuclear plant last year sent shock waves across the world.

Beijing suspended approval of new nuclear power projects following the massive earthquake and tsunami in March 2011, that triggered a radiation leak at Japan's Fukushima Daiichi nuclear power plant.

But now China's nuclear program is getting back on track.

Nuclear program will bring more power

Employees in the control center of Tianwan Nuclear Power Plant in Lianyungang, Jiangsu province. Wang Jianmin / CFP

The Ministry of Environmental Protection heralded this development in late November with two announcements: The Qinshan Nuclear Power Plant in East China's Zhejiang province will launch a flood-control project, and the Tianwan Nuclear Power Plant in Jiangsu province, also in East China, will build two nuclear power reactor units.

The State Council passed the Nuclear Power Safety Plan (2011-20) and the Mid- and Long-Term Development Plan for Nuclear Power (2011-20) on Oct 24. Eight days earlier, it approved the 12th Five-Year Plan (2011-15) for Nuclear Safety and Radioactive Pollution Prevention and Vision for 2020. These three documents paved the way for the nation to relaunch its nuclear power projects.

Fifteen nuclear power reactors had entered service by the end of 2011, with a total installed capacity of 12.54 million kilowatts. Another 26, still under construction, were designed with a combined installed capacity of 29.24 million kW, the largest in the world. The country's installed nuclear power capacity is expected to reach 40 million kW by 2015, according to China's Energy Policy 2012 published by the Information Office of the State Council on Oct 24.

"It takes about five years to build a nuclear power generating unit," said Pu Jilong, a senior expert in nuclear and radiation safety and former deputy general manager of China Guangdong Nuclear Power Holding Co. "Now that the government has started ratifying new nuclear power projects, if four units are approved each year, the total installed capacity is likely to reach 60 million kW by 2020."

Previous Page 1 2 3 4 Next Page

Hot Topics

Editor's Picks
...
主站蜘蛛池模板: 色妞色视频一区二区三区四区| japanese老熟妇乱子伦视频| 欧美一级视频在线| 免费国产不卡午夜福在线 | 日韩a一级欧美一级| 亚洲国产精久久久久久久| 狠狠色丁香婷婷| 公和我乱做好爽添厨房中文字幕| 色播亚洲视频在线观看| 国产在线视频99| 久碰人澡人澡人澡人澡人视频 | 久夜色精品国产一区二区三区| 欧美日韩亚洲区久久综合| 人人妻人人澡人人爽欧美精品| 精品国产午夜理论片不卡| 国产v亚洲v天堂a无码| 饭冈加奈子黑人解禁在线播放| 国产真实乱xxxav| 在线国产你懂的| 国产精品污视频| 78成人精品电影在线播放 | 一级一级特黄女人精品毛片| 无码一区二区三区在线| 久久久精品人妻无码专区不卡 | 深夜a级毛片免费视频| 免费毛片在线播放| 精品久久久久久无码中文野结衣| 喝乖女的奶水h1v| 羞差的漫画sss| 喷出巨量精子系列在线观看| 丰满少妇被粗大猛烈进人高清| 短篇丝袜乱系列集合嘉嘉| 午夜福利一区二区三区高清视频| 老司机67194免费观看| 国产一区二区三区美女| 调教视频在线观看| 国产在线19禁在线观看| 黑白禁区高清免费观看全集电视剧| 国产清纯白嫩初高生在线观看性色| 亚洲自拍欧美综合| 国产精品538一区二区在线|