Kenya launches Chinese-built fast train

China Daily Africa | Updated: 2017-05-28 08:23

The eagerly awaited inauguration of Kenya's modern railway infrastructure is set for May 31. The $3.8 billion Standard Gauge Railway, developed by China Road and Bridge Corp, has been completed six months ahead of schedule. It is expected to lower the cost of doing business in East Africa as it enables the transportation of freight from the port of Mombasa to Nairobi, with later connections to neighboring Uganda and Rwanda.

Here is a chronology of the milestones of the 472 km Nairobi-Mombasa route:

Phase I

Aug 12, 2009: CRBC signed MoU with Kenya Railways Corp.

2012: Submitted the preliminary design. Civil works contract and supply and installation of facilities, locomotives and rolling stock contracts signed.

Aug 19, 2013: President Xi Jinping and President Uhuru Kenyatta jointly witnessed the signing of the MoU on financing the Mombasa-Nairobi SGR Project.

May 11, 2014: Premier Li Keqiang witnessed the signing of the financing agreement with heads of state from East African countries.

Phase II

Dec 12, 2014: Project construction officially commenced.

Jan 23, 2015: Kenyatta visited the standard gauge railway observation segment of Section 3, and track-laying base of Section 6.

May 26, 2015 : Kenyatta visited the construction site of the Tsavo River Super Bridge.

Sept 19, 2015: Kenyatta and China Communications Construction Co President Chen Fenjian jointly attended the ground-breaking ceremony of the Nairobi Terminus.

Oct 30, 2015: Track-laying work commenced and operation planning and locomotive purchase started.

March 26, 2016: Zhang Dejiang, chairman of the Standing Committee of National People's Congress, went to Mombasa to see the Mombasa Terminus of Mombasa-Nairobi SGR Project.

Aug 10, 2016: Kenyatta met with Chinese Foreign Minister Wang Yi in Nairobi, showing willingness to actively promote the early completion and operation of the project and jointly build the East Africa Railway Network.

Late December 2016: The first locomotives were shipped.

Phase III

Beginning of 2017: Integration test and commission started.

June 1, 2017: Trial operation of SGR Project.

January 2018: Officially opened to traffic.

 Kenya launches Chinese-built fast train

Thousands of young men and women have had the chance to be part of the team behind the success of the Standard Gauge Railway Project.

?

?

 

Polar icebreaker Snow Dragon arrives in Antarctic
Xi's vision on shared future for humanity
Air Force units explore new airspace
Premier Li urges information integration to serve the public
Dialogue links global political parties
Editor's picks
Beijing limits signs attached to top of buildings across city
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
主站蜘蛛池模板: 91亚洲精品自在在线观看| 中文在线观看视频| 欧美日韩国产在线人成| 免费a级毛片在线播放| 老司机亚洲精品影视www| 国产在线不卡视频| 人人干人人干人人干| 国产美女视频网站| 99精品在线视频观看| 好男人影视官网在线www| 中文字幕在线不卡| 日本中文字幕有码视频| 久久精品一本到99热免费| 欧洲一区二区三区在线观看| 亚洲女成人图区| 欧美色图第三页| 亚洲精品乱码久久久久久按摩| 男人把大ji巴放进男人免费视频 | 亚洲图片国产日韩欧美| 热99精品在线| 免费A级毛片在线播放不收费| 精品国产自在现线看| 嘟嘟嘟www在线观看免费高清 | 精品国产免费观看久久久 | 国产精品人成在线播放新网站| 手机在线观看你懂的| 天天爽夜夜爽人人爽| 一区二区三区在线看| 成人免费视频一区二区三区| 丰满少妇被猛烈进入高清播放| 日本无遮挡h肉动漫在线观看下载| 久久精品综合一区二区三区| 曰韩无码无遮挡a级毛片| 五月婷婷综合在线| 最近中文字幕免费4| 五月天婷婷在线观看视频| 果冻传媒mv在线观看入口免费| 亚洲xxxxx| 李宗瑞60集k8经典网| 亚洲AV无码一区东京热| 最近日本中文字幕免费完整|